A used machine order moves through four stages, and only one of them is under our control. Understanding which stage is currently running tells you more about the ship date than any headline number.

What are the four stages between your deposit and delivery?

StageWhat happensWho controls the pace
1. Selection and inspectionYou pick a machine from our list or we source to your spec; we shoot a start-up video with the serial number visibleYou — how fast you approve
2. PreparationService, replacement of worn parts if agreed, cleaning, photographyUs and the workshop queue
3. BookingSpace on a vessel to your port; flat rack or container confirmedThe shipping line — this is the stage that slips
4. Loading and documentsMachine blocked and lashed, photos taken, B/L issued after departurePort and forwarder

Where the delay actually comes from

Not from the workshop. Booking is the variable: space to smaller ports is not daily, and the weeks before Chinese New Year are the worst of the year for availability and rate. If your project has a hard date, tell us the date first and we will work backwards from the vessel rather than forwards from the machine.

What "in stock" does and does not mean

In stock means the machine is physically at a yard in China and can be inspected this week. It does not mean it is loaded and gone. A machine that is already sold to someone else stays on a listing until the deposit clears, so always ask whether the unit in the photo is still available before you plan around it.

How to get a reliable date from us

Ask for the vessel and the port, not a promise. We quote the sailing we are actually booking against and name the line. If the date moves, you hear it from us on the day it moves, not after the cut-off.

The calendar that actually affects your date

Chinese manufacturing and logistics shut down around the Lunar New Year, and slow down around the National Day holiday in early October. In the four to six weeks before Lunar New Year, vessel space tightens and rates rise; factories also finish orders early and stop accepting new ones. If your machine must arrive before a construction season starts, work backwards from that season, not forwards from today.

WindowWhat to expectWhat to do
4–6 weeks before Lunar New YearSpace tight, rates up, workshops fullBook early or accept the following month
Lunar New Year weeksWorkshops closed, ports reducedDo not plan loading in this window
Early OctoberShort holiday shutdownConfirm cut-off dates in advance
Quiet monthsBetter rates, more sailing choiceUse it for stock building

What we do when a vessel slips

We tell you the same day and offer the next sailing with its date, or a different port pair if that gets you there sooner. What we do not do is stay silent and let the original date stand — that is how buyers end up with a machine sitting at a terminal while their crew waits on site.

How to keep the process short

Three things speed up a used machine order more than anything else: approving the inspection video fast, sending the import document list early, and naming one person on your side who can say yes. Orders that stall usually stall on approvals, not on machines.

Questions buyers ask before ordering

How long does shipping take after I pay the deposit?

It depends on the vessel, not on us: preparation is a workshop task measured in days, while space to your port may be weekly or less frequent. We quote against a named sailing so the date is checkable rather than optimistic.

Is a machine listed as in stock really available?

It is at a yard and can be inspected this week. It stays listed until a deposit clears, so confirm availability before you build a plan around a specific unit.

Can you hold a machine while I arrange finance?

We can hold a unit for a short period against a deposit, and we say plainly how long the hold runs. Holding without a deposit is not something we do, because it blocks the machine from other buyers.

What documents arrive after departure?

Bill of lading, commercial invoice, packing list and certificate of origin, plus photos of the blocked and lashed machine. Certificates your country requires are arranged before shipment, not after.

Last verified: 2026-11-06 · Sources: export documents on file, shipping line schedules, port authority notices.

Ask about a specific machine WhatsApp +86 136 1161 8158

WhatsApp us